Preparing for Building
Up Preparations Obtaining the Site Preparing for Building Building Process Official Opening New building in use Requirements and Plans Financial Statement

wpe1.gif (9521 bytes)

Previous Pages

Home
SSB History
SSB Philosophy
SSB Trust
Our own Building
Table of Contents

Seliba Sa Boithuto

 

 

Postal Address:

P.O.Box 288

Maseru 100

LESOTHO

 

 

Email Address:

mathot@lesoff.co.za

 

 

Physical Address:

Ha Tsautse

Main South Road

Maseru

LESOTHO

 

 

Banks:

NedBank (Lesotho)

SSB

#:027/06/3925/11

 

Postbank

Amsterdam

Seliba Sa Boithuto Bouwfonds

  # 684 99 27

 

Standard Bank (Lesotho)

SSB Trust

# 0140097462501

 

Preparing the Site for Building

The site consists of two levels:

  • a flat area above, where the Leuna Lechesa Building is situated and
  • a rocky triangular area below, where rondavels can be built in future for small group learning and a hall for larger activities. Because of the vegetation on the lower area, it can also be pleasantly used for out-door studies and meetings.

The site can be reached by car on a dirt road, branching off from the Maseru-by-pass, reaching the site on top. On foot it can be reached from below.

Piped water, electricity and telephone connections are near the site. Water and electricity have been connected by WASA and LEC respectively, but a telephone line still needs to be connected. Town sewerage is not available and also, because the rocks on the site do not allow drainage, it was decided to build EnviroLoo dry toilets.

 

 

 

To prepare for building we constructed a fence, a footpath and equalized the site. Then we contracted Dr Peter Hancock to make the architectural drawings and obtained the Building Permit from the Maseru City Council.

History of Preparing the Site for Seliba Sa Boithuto

August 2001

Topo Survey by Property Surveyors

March 2002

Security Fence and gates completed by PLM Construction

August 2002

Permission to build a footpath by Mr Thuoang

February 2003

Completion of Footpath by KPL Construction

February 2003

Death of 1st Architect, Mr Sekhoane Pokane

April 2003

Levelling the site by KPL Construction

May 2003

Contract Dr Peter Hancock to make Architectural Drawings

October 2003

Completion of Architectural Drawings

go to THE BUILDING PROCESS