History
of the Building the Leuna Lechesa Building
|
|
March 2004
|
Granting
of Building Permit by the Maseru City Council
|
|
March 2004
|
Signing
of building contract with Twentieth Century Construction Company
|
|
March 2004
|
Setting
out of the building and digging foundations
|
|
April 2004
|
Arrival
of EnviroLoo Toilet sets from Johannesburg
|
|
April 2004
|
Start
of building the Toilet Block of 4 toilets
|
|
April 2004
|
Building
the foundations
|
|
May 2004
|
Building
the walls
|
|
June 2004
|
Installing
the windows
|
|
July 2004
|
Making
Roof Structure
|
|
August 2004
|
Start
of thatching
|
|
September 2004
|
Completion
of Toilet Block
|
|
September 2004
|
Planned
Completion Date
|
|
September 2004
|
Construction
of retaining wall for and floor of the terrace
|
|
October 2004
|
Painting
the inside walls
|
|
November 2004
|
Laying
floor tiles
|
|
November 2004
|
Electrical
wiring
|
|
December 2004
|
Plumbing
|
|
December 2004
|
Completion
of thatching
|
|
December 2004
|
Installation
of fence around the terrace
|
|
January 2005
|
Installation
of Lightning Conductors
|
|
January 2005
|
Installation
of alarm system
|
|
January 2005
|
Official
Opening of the Leuna Lechesa Building
|
|
February 2005
|
Some
final touch-ups
|
|

Digging the foun-dations, using a pneumatic drill
|

Pouring
the foundation slab
|
|

Building
the foun-dations. See the double wall
|

Building
both the inside block and the outside sandstone walls.
|
|

Building
the Enviro-Loo dry toilets |

The
Toilet Block completed
|
|

Installing
the windows
|

Building
the retaining wall for the terrace
|
|

Making
the roof structure
|

Thatching
in progress
|
|

The
water basin outside
|

A
view through the window on the terrace
|
|

Painting
(See Trombe Walls)
|

Laying
the floor tiles
|

Bringing
the furniture
|
|

Installing the electrical fittings
|

The
fence and the terrace
|
|

Overlooking
Maseru
|

A
view from below
|